HS2 ‘is a £28 billion project’

leave a comment »

HS2 is ‘not a £42 billion project’, it is a ‘£28 billion project with a 50% contingency attached’, Andrew Adonis told the Lords Economic Affairs Committee on 11 November 2014 [from about 17:14:34 on the video].

Andrew Adonis speaks to the Lords Economic Affairs Committee, 11 Nov 2014

Written by beleben

July 29, 2019 at 11:35 am

Posted in HS2