How reliable are HS2 cost estimates?

with 5 comments

Earlier this month, the cost of HS2’s proposed Washwood Heath rolling stock facility was officially estimated at £51 million (2nd quarter 2011 prices), i.e., less than half the cost of the (smaller) Calvert infrastructure depot.

HS2 London – West Midlands cost estimate, January 2015 (source: HS2 Ltd)
Element £m (2Q 2011)
1.0 Land and property 1.1 London Euston 579.82
1.2 London Metropolitan 221.96
1.3 Country South 319.12
1.4 Country North 306.09
1.5 West Midlands Metropolitan 315.50
Sub total 1742.48
2.0 Tunnel works 2.1 Tunnels 2427.17
2.2 Portals 213.02
2.3 Shafts 358.13
Sub total 2998.32
3.0 Civil engineering 3.1 Cuttings and embankments 1309.00
3.2 Retaining walls 339.29
3.3 Bridges 450.95
3.4 Viaducts 836.89
3.5 Roads and pavings 391.91
3.6 Other structures 352.78
Sub total 3680.82
4.0 Stations 4.1 Euston 1506.37
4.2 Old Oak 798.84
4.3 Birmingham interchange
(Bickenhill)
277.08
4.4 Curzon 283.58
Sub total 2865.87
5.0 Depots and stabling 5.1 Washwood Heath 51.01
5.2 Calvert 136.62
5.3 Heathrow Express relocation 152.87
5.4 London sidings 0
5.5 Other facilities 96.96
Sub total 437.47
6.0 Railway systems 6.1 P-way 546.56
6.2 Signals 113.30
6.3 Telecoms 93.02
6.4 Electrical contact systems 162.62
6.5 Electrical distribution
equipment
422.82
6.6 Station and depot systems 192.31
6.7 Tunnel systems 167.81
Sub total 1698.44
7.0 On-network works 7.1 Civil engineering 0
7.2 Stations and depots 0
7.3 Railway systems 528.67
Sub total 528.67
8.0 Indirect costs 8.1 Corporate 1002.99
8.2 Project management 820.58
8.3 Design 395.36
Sub total 2218.93
Gross point estimate 16171.01

For comparison,

  • Eurostar’s Temple Mills depot cost ‘up to’ £402 million, according to Lord Davies of Oldham (Hansard, 1 December 2004)
  • Network Rail’s South Wales resignalling was estimated at £400 million in 2011
  • the ‘Birmingham Gateway’ refresh of the existing New Street station was budgeted in excess of £600 million.
Advertisements

Written by beleben

January 30, 2015 at 11:18 am

Posted in High speed rail, HS2

Tagged with

5 Responses

Subscribe to comments with RSS.

  1. Can you point me to the link for the source of this information please? I will do you a swap! Point 15 of this link shows the Washwood Heath cost to be £374.9m!!!

    http://www.parliament.uk/documents/commons-committees/hs2/Letter_to_Neil_Caulfield_re_Petition_295.pdf

    Joe Rukin

    February 5, 2015 at 9:17 am

  2. Is that published anywhere?

    Joe Rukin

    February 5, 2015 at 1:04 pm

    • I don’t know. You could ask HS2 Ltd to update their foi response disclosure, if they’re not up to date.

      beleben

      February 5, 2015 at 3:02 pm

      • Yeah, the problem with that is that I am up in front of the Bill Committee on Monday and want to use this! The HS2 Ltd FOI disclosure has gone AWOL with the site migration and i somehow doubt they would get it to me in time if I asked. If it can be emailed to me or Penny, that would be great!!!

        Joe Rukin

        February 5, 2015 at 5:30 pm


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: